Date: 19 September – 14 October 2022

Area: Swellendam and Railton

RoadFrom To
Buitekant StreetMoolman StreetMoolman Street
Murray StreetColdrey Street
Murray StreetMurray Street
Drostdy StreetKerk StreetDe Mist Street
De Mist StreetHoop Street
Hoop StreetFairbairn Street
Fairbairn StreetCul de Sac
Hoop StreetDrostdy StreetCul de Sac
Jansens StreetBuitekant StreetBuitekant Street
Kamp StreetHermanus Steyn StreetKeerom Street
Keerom StreetKerk StreetKerk Street
Kamp StreetKamp Street
Kromberg StreetVan Staden StreetVan Staden Street
Mitchell Whyte StreetVoortrek StreetBuitekant Street
Moolman StreetVoortrek StreetVoortrek Street
Buitekant StreetMike Müller Street
Scholtz StreetHeyns StreetRhenius Street
Rhenius StreetCul de Sac
Hermanus Steyn StreetHeemraad StreetKerk Street
Visser StreetHeyns StreetHeyns Street
Rhenius StreetRhenius Street
Cooper StreetN2 LinkStation Street
Andrew Whyte StreetBaker StreetBuirski Street
Bontebok StreetVollenhoven StreetProtea Street
Reisiebaan StreetRailway crossing
Voortrek StreetShand StreetVon Manger Street

 

Reason: Resealing of Roads

Notice is hereby provided of resealing and rehabilitation work which will be undertaken in the above-mentioned areas as of 19 September to 14 October 2022.

The construction period is estimated at 15 days, but an additional 5 days have been added to the schedule to make provision for weather conditions and any contingency plans should the need arise. We urge residents to make use of alternative routes and parking where necessary, as affected streets will be partially closed. Residents in affected streets will have access to their property.

Please accept our sincere apology for any inconvenience caused and request residents to please obey any road and/or traffic construction signs.

A. VORSTER
ACTING MUNICIPAL MANAGER

Notice No: A44/2022

15 September 2022